Quarter 1 - 2024
January 2024 - March 2024
- Strategic Planning committee formalized.
- Strategic Planning Steering Group formalized.
- Workplan for SPC is finalized (Approved by SG)
Quarter 2 - 2024
April 2024 - June 2024
- SPC Support Staff & Space Allocated
- Communication of SP Process via Omni Channel
- Data Collection: all existing Policies, Mini Plans, & SOPs
- Stakeholder Consultations and Results
- Gap Analysis of Culture, Vision, Mission, SWOT & STEEP
- Strategic Areas, Objectives & Strategic Plan’s Outline Prepared (Approved by SG)
Quarter 3 - 2024
July 2024 - September 2024
- Discovery Session held with stakeholders to contribute to the development of the SP30
- Data Analysis and Cleaning
- SAs’ Strategies, Actions, KPIs, Resources, & Owner Built
- Strategic Area Team (SAT) and their TORs established (Approved by SG)
Quarter 4 - 2024
October 2024 - December 2024
- SATs started development of "Strategic Area" Documents
- SPC Work progress presented in 119th BoG meeting held on October 21, 2024
- Strategic Area Team (SAT) submitted "Strategic Area" Documents
- The 32nd Academic Council Meeting held in conjunction with Strategic Planning Committee on December 06, 2024
Quarter 1 - 2025
January 2025 - March 2025
- Compilation of data into Standardize Document Template
- Draft Version presented to Dean’s Council and HoD’s
- Discussions with multiple stakeholders regarding KPI’s and Actions
Quarter 2 - 2025
April 2025 - June 2025
- SP30 draft report to be presented to complete IBA Community
- Updated SP30 report will be presented to BoG